CASE HISTORY



The company C. had to chose if it was preferable to use pre-terminated cables or to assemble connectors "on field" in an Ethernet installation. Typical links were 30m long, with one hundred links overall.

It was made the following table:

Laying time Termination time Total laying time Total termination time
Pre-terminated cables 40 meters/hour 0 100(sections)*30(m)/40(meters/hour) = 75 hours 0
Non- terminated cables 60 meters/hour 3min 100(sections)*30(m)/60 (meters/hour) = 50 hours 200connectors*3min

While the non-terminated cables appeared preferable, both in terms of installation time and costs (a pre-terminated cable is more expensive and often longer than needed), the choiche went to pre-terminated cables, because field-mounted connectors weren't reliable.

By using plastic fiber, it discovered that a work which required 10 working days could be carried out in less then 4 days:

Laying time Termination time Total laying time Total termination time
Plastic fiber 100 meters/hour 0,5min 100(sections)*30(m)/100(meters/hour) = 30 hours 200connectors*0,5min = 1,6 hours